| Instructions |
 |
Install the C.T in the middle
phase of the alternator output, before the plant load and
the SmartLoad load bank connection. Use 1.5mm or 18# cable. |
 |
Connect wires to terminals
1 and 2. |
 |
Terminals 3 & 4 are
factory looped which will activate the load bank when power
is activated from the generator set. If an interlock is
required to activate the the load bank at a predetermined
time, install a voltage free contact off the generator
main circuit breaker or contactor or system changeover
switch, to signal the SmartLoad bank to start or to shutdown
when required. Remove the loop wire off terminals 3 & 4
and connect to the voltage free contact. |
 |
Connect 110/120V (active & neutral)
supply to terminals 5 & 6 for the control circuit operation
of the load bank. |
 |
Connect the SmartLoad bank
in parallel with the plant load. This connection should
be after the C.T. The C.T. must read the total current
of the load bank and the plant load. Connect appropriate
size cables (refer CABLE CHART) from the A, B, and C terminals
on the SmartLoad bank to the A, B, c terminals of the plant
load connection. |