RCI Series Load Bank Electrical Connection
The SEPHCO SmartLoad load bank is supplied complete with C.T.
for wiring to the generator output terminals.
 
Instructions
Install the C.T in the middle phase of the alternator output, before the plant load and the SmartLoad load bank connection. Use 1.5mm or 18# cable.
Connect wires to terminals 1 and 2.
Terminals 3 & 4 are factory looped which will activate the load bank when power is activated from the generator set. If an interlock is required to activate the the load bank at a predetermined time, install a voltage free contact off the generator main circuit breaker or contactor or system changeover switch, to signal the SmartLoad bank to start or to shutdown when required. Remove the loop wire off terminals 3 & 4 and connect to the voltage free contact.
Connect 110/120V (active & neutral) supply to terminals 5 & 6 for the control circuit operation of the load bank.
Connect the SmartLoad bank in parallel with the plant load. This connection should be after the C.T. The C.T. must read the total current of the load bank and the plant load. Connect appropriate size cables (refer CABLE CHART) from the A, B, and C terminals on the SmartLoad bank to the A, B, c terminals of the plant load connection.

Specifications and information subject to change without notice. E & OE