| Load Bank Installation
Details |
 |
| • |
|
The load bank is to be installed
in a location that provides approximately 36" (1 Metre)
of unobstructed clearance around all sides of the machine.
This is to allow for:- |
 |
| • |
|
Sufficient unrestricted air
flow into the intake chamber(s) in the base of the machine
for necessary cooling. |
 |
| • |
|
Sufficient space to open the
access doors at the front of the machine and to allow for resistor
replacement from the rear. |
 |
| • |
|
Vertical fan cooled load banks
must not have any overhanging roofs or awnings which may restrict
or disturb air discharge. |